Concrete frame construction to block A is steadily progressing and should be completed to roof level by December 2019. Perimeter scaffolding for the construction of the block A brickwork façade will be erected during October 2019.


Bulk excavation of the basement for blocks B, C, D and E is complete, and consequently air monitoring will now be suspended until excavation works recommence for the service corridor area.


Concrete construction works for blocks B, C, D and E foundations are ongoing and should be completed in September 2019. This will be followed by concrete frame construction works from basement level to roof level. We anticipate that these works will be ongoing until the end of February 2020. The perimeter scaffold construction works
to blocks B, C, D and E for the brickwork façade will begin in early December 2019.